One planned surgical admission is exposed
E. Baker's Ward S4 discharge path is the operating constraint for A. Khan and Theatre 2.
- Run
- Active run 09:15
- Source
- 09:12
- Profile
- Default morning protection
- Rules
- r1 / p1
Exposure ledger
24 cases in run scopeE. Baker
Ward S4 / Bed 12- Predicted ready
- 13:45
- Required ready
- 12:45
- Variance
- 60 min after required ready
- Probability
- 82%
Predicted 13:45 versus required 12:45; 60 min after required ready.
Protected chain
- E. BakerDischarge caseExpected discharge 10:30
- Ward S4 / Bed 12Bed dependencySame bed group release
- A. KhanPlanned admissionPlanned arrival 12:00
- 12:45Bed ready byRequired before pre-op flow
- Theatre 2Theatre listScheduled start 14:00
- ExposedOutcomePredicted bed ready 13:45
Current blockers
2-4 hours- TTOPharmacy
- In progress120 min escalation windowRequested 08:05; unresolved 75 min before expected discharge
- TransportTransport
- In progress120 min escalation windowRequested 08:40; backup option not confirmed
- Discharge summaryWard Administration
- In progress90% completion floorUpdated 08:55 at 60%; floor is 90%
- PhysioTherapy
- CompleteRequired before releaseCompleted 08:20
Escalate pharmacy
TTO is unresolved inside the configured escalation window.
- Expected effect
- Expected delay reduction 60 min
- Recipient
- Lewis Graham / Pharmacy